How Does Google Get a Gigawatt of Power?
Amin Vahdat says Google's preferred model for a new data center is to stay connected to a utility, even when the site needs a gigawatt of power. A gigawatt is not a request for tomorrow followed by a question about when billing starts. Google co-plans with the utility and gives many years of notice.
Google covers the cost of transmission lines that must be built or upgraded and of additional utility base stations. The reason is billing: if the utility builds capacity for Google, other people's rates could go up. Planning can still leave a gap. In a made-up example, Google needs a gigawatt in 2028, the utility can supply a gigawatt in 2029, and can supply 700 megawatts in 2028. Covering the other 300 megawatts can mean waiting, or generating some power on site with solar cells, batteries as backup, or other sources, while still working with the utility.
Local generation can remain after the utility reaches full gigawatt scale, with the capability to send power back to the grid.
Google's AI Infrastructure Chief, Amin Vahdat, on the Physics & Economics of Frontier AI ·