Why Was 20% of Vogtle's Nuclear Cost Overrun Just Interest?
Scott Nolan says interest during a long construction job, not the famous accidents, is a large part of why American nuclear plants got so expensive. Vogtle ran far over budget and behind schedule. About 20 percent of that cost overrun was interest, and that was in a period of historically low rates. When a plant takes about 10 years to build, the overnight construction cost matters less than the interest paid while it sits unfinished. His fix for the big reactors is to build them faster and to build more of them, so the work finally gets economies of scale.
John Collison points to the 1970s slowdown, when mortgage rates reached about 18 percent in 1981 and the cost of capital was well north of 10 percent. Nolan treats Three Mile Island and Chernobyl as a slight pause that gets blamed for the whole stall. The deeper problem is that the electricity was not cheaper. Nuclear is the cleanest and safest baseload, and it still has to win on price.
The company building America’s uranium supply from scratch ·
From the transcript
If we're talking about power on the ground, I think nuclear still wins, whether that's data center, industrial, whatever it is. How will cost get solved or will it get solved? It will get solved. And then the way it gets solved depends on what you think the cause of the cost issues in nuclear being. So this is one of those over-determined problems of like, why haven't we scaled nuclear? I think most people just say safety.
You know, they look back to the 70s and they say, there was a movie, The China Syndrome, you had Three Mile Island, you had Chernobyl. And so clearly nuclear was going to stop and we wouldn't scale it. And I do think the scaling piece is actually one of the proximate causes. We never hit economies of scale. We weren't doing it quickly enough.